June 22, 2016 at 14:23 EDTPennDOT
A bridge replacement project on Route 239 between Maple Lane and Klinger Hill Road in Sugarloaf Township, Columbia County, is set to begin Monday, June 27.
Work includes removal of the existing structure and construction of a single span pre-stressed concrete box beam bridge, drainage improvements and the installation of guide rail.
A detour will be in place using Route 487, Camp Lavigne Road and Route 118.
Work is expected to be completed in October.
Ryland Construction Company, Inc., is the prime contractor on this $1.1 million project.
June 21, 2016 at 13:58 EDTPennDOT
A microsurfacing project on Route 1004 (Old Berwick Road) in Columbia County is scheduled to begin tomorrow, Wednesday, June 22.
Work will be between Route 487 in the Town of Bloomsburg and Route 2028 (Market Street) in South Centre Township.
Traffic will be reduced to one lane under daylight flagging operations.
Vestal Asphalt, Inc., is the prime contractor on this project.
Work is expected to be completed in July, weather permitting.
June 10, 2016 at 19:30 EDTCCS
SCOTT TOWNSHIP – An officer attempted to stop a Pontiac sedan shortly before 1 AM Friday in the area of Tenny St & Old Berwick Rd, but the driver fled at a high rate of speed on Riverview Ave.
One person fled on foot after the vehicle wrecked at the dead end of Worman St.
April 29, 2016 at 12:47 EDTPennDOT
On Monday, May 2, a 3.4-mile micro-surfacing project on Route 254 in Columbia County will begin.
Work will be from Taylor Road in Millville Borough to Route 44 in Madison Township.
There will be daylight signing and flaggers providing traffic control.
Work is expected to be completed in late June.
Suite-Kote Corporation is the prime contractor on this $237,500 project.
April 28, 2016 at 15:31 EDTPennDOT
On Monday, May 2, a PennDOT maintenance crew in Columbia County will begin widening Route 3016 (Hollow Road) in Catawissa Borough and Catawissa Township.
Work is expected to be completed by Thursday, May 5, weather permitting. The road will be closed from 6 a.m. to 6 p.m. each day.
A detour will be in place using Route 42 and Route 487.
April 21, 2016 at 16:47 EDTPennDOT
Update: All lanes of Route 339 are open.
Motorists in Columbia County are advised that Route 339 is down to a single lane between Mainville and Mifflinville due to a vehicle crash and downed power lines.
Flaggers are directing traffic through the area.
Motorists can check conditions on more than 40,000 roadway miles by visiting www.511PA.com. 511PA, which is free and available 24 hours a day, provides traffic delay warnings, weather forecasts, traffic speed information and access to more than 770 traffic cameras.
April 19, 2016 at 15:19 EDTPennDOT
On Monday, April 25, a PennDOT bridge crew in Columbia County will begin a bridge replacement project on Route 4008 (Back Branch Road) in Mount Pleasant Township.
The existing concrete slab bridge, which spans a tributary of Fishing Creek, was built in 1940 and is classified as functionally obsolete. It will be replaced with a box culvert.
The bridge will be closed during the project. Route 4013 (Whites Church Road) also will be closed due to its close proximity to the bridge.
March 22, 2016 at 15:40 EDTPennDOT
Update: The ramp is open as of 19:05.
Motorists in Columbia County are advised that the northbound ramp from Route 11 to Route 42 north is closed due to a tractor-trailer rollover.
The ramp is closed and traffic is being detoured to Route 11 and the Town of Bloomsburg.
Motorists can check conditions on more than 40,000 roadway miles by visiting www.511PA.com. 511PA, which is free and available 24 hours a day, provides traffic delay warnings, weather forecasts, traffic speed information and access to more than 770 traffic cameras.
March 17, 2016 at 14:17 EDTPennDOT
A multi-year, $30 million project is set to resume next week on Interstate 80 in Montour County.
On Monday, March 21, prime contractor Glenn O. Hawbaker Inc. will set up traffic control devices in the westbound lanes of the interstate from the Columbia County line to the Danville/Route 54 Interchange.
On Tuesday, Wednesday and possibly Thursday, the contractor will mill and fill rumble strips in the westbound left shoulder throughout the work zone. Traffic will be reduced to a single lane while this work is being performed.
February 29, 2016 at 18:03 ESTPennDOT
6:45 PM Update... Both lanes of I-80 EB are now open.
Motorists in Columbia County are advised that the passing lane of Interstate 80 eastbound is closed just east of Light Street.
Motorists should be alert for slow-moving traffic and drive with caution through the area.
Motorists can check conditions on more than 40,000 roadway miles by visiting www.511PA.com. 511PA, which is free and available 24 hours a day, provides traffic delay warnings, weather forecasts, traffic speed information and access to more than 770 traffic cameras.